Rolling Wave Planning: Milestones Creation

When are milestones created in rolling wave planning?

A) Milestones are created at the beginning of the project. B) Milestones are created throughout the project as more details become available. C) Milestones are created at the end of the project. D) Milestones are not used in rolling wave planning.

Answer:

In rolling wave planning, milestones are set throughout the project as more details are revealed, allowing for more precise planning in increments. So the correct answer is option (B).

Explanation: In rolling wave planning, milestones are created throughout the project as more details become available. This approach to project management involves planning and scheduling the project in waves as the project evolves and more information is uncovered. Initially, the project team plans out the near-term activities in detail and high-level plans for future activities. As the project progresses and the team gains a better understanding of upcoming work, they define more detailed plans and thus create additional milestones. Option B) Milestones are created throughout the project as more details become available is the correct answer, as it best describes the nature of how milestones are used in rolling wave planning.

← Data land usa the silicon valley phenomenon 100 fun facts about cats →